| Eslam Abad | 2*162MW(G.T) + 1*160MW(S.T) | 2009 | 2009 | MAPNA Co. | | |
|
| 22CC - Damavand | 6*160 MW | 2008 | 2010 | MAPNA Co. | | |
|
| Pareh Sar | 4*160MW(G.T)+2*160MW(S.T) | 2008 | 2010 | MAPNA Co. | | |
|
| Kahnouj | 484 MW | 2008 | 2011 | MAPNA Co. | | |
|
| Genaveh | 484 MW | 2008 | 2011 | MAPNA Co. | | |
|
| Pareh Sar Thermal(Gas Turbine & Steam Turbine Portion) | 4*160 MW(G.T)+2*160 MW(S.T) | 2007 | 2010 | MAPNA Co. | | |
|
| 22CC - Sanandaj | 2*160 MW | 2007 | 2011 | MAPNA Co.(MD2) | | |
|
| 22CC - Shirvan | 3*160 MW | 2007 | 2011 | MAPNA Co.(MD2) | | |
|
| 22CC - Jahrom | 3*160 MW | 2007 | 2011 | MAPNA Co.(MD2) | | |
|
| Site Engineering Services-Sanandaj | 2*160 MW | 2007 | 2010 | MAPNA Co. | | |
|
| Site Engineering Services-Shirvan | 3*160 MW | 2007 | 2011 | MAPNA Co. | | |
|
| Site Engineering Services-Jahrom | 3*160 MW | 2007 | 2011 | MAPNA Co. | | |
|
| Teshreen | 2*150 MW(G.T)+1*150 MW(S.T) | 2007 | 2010 | MAPNA Co. | | |
|
| Abadan | 2*160 MW | 2007 | 2011 | MAPNA Co. | | |
|
| Damavand | 6*160 MW | 2006 | 2008 | MAPNA Co.(Eng. Deputy) | | |
|
| Yazd Solar-Thermal(Gas Turbine & SteamTurbine Portion) | 2*159 MW(G.T)+1*160 MW(S.T) | 2006 | 2009 | MAPNA Co. | | |
|
| Site Engineering Services-Damavand | 6*160 MW | 2006 | 2011 | MAPNA Co. | | |
|
| Site engineering Services Yazd STTP | 2*159 MW(G.T)+1*160 MW(S.T) | 2006 | 2010 | MAPNA Co. | | |
|
| 22CC - Kerman | 4*160 MW | 2005 | 2007 | MAPNA Co. | | |
|
| 22CC - Kazeroon | 3*160 MW | 2004 | 2007 | MAPNA Co. | | |
|
| 22CC - Yazd | 1*160 MW | 2003 | 2006 | MAPNA Co. | | |
|
| 22CC - Neka | 1*160 MW | 2003 | 2006 | MAPNA Co. | | |
|
| 5CC - Shariati | 1*105 MW | 2000 | 2003 | MAPNA Co. | | |
|
| 5CC - Neyshabour | 3*105 MW | 1999 | 2003 | MAPNA Co. | | |
|
| 5CC - Fars | 3*105 MW | 1998 | 2003 | MAPNA Co. | | |